Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
▸Direct Field Costs$385.9M
CO2 absorption$79.6M
Civil structural work$46.9M
General utility system$51.3M
CO2 Compression Equipment$43.3M
Flue Gas Conditioning$52.4M
Solvent regeneration$40.7M
Stack connection and modification$15.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary system$55.7M
▸Indirect Field Costs$57.1M
Construction preliminaries$34.7M
Engineering$10.4M
Mechanical completion, commissioning and testing$13.1M
Training$1.0M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction$27.0M
Report did not provide a further cost breakdown.
▸Owners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M
Linde Hydrogen Plant
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
18.3%mol%
▸Direct Field Costs$327.0M
Carbon Capture Plant$110.0M
Construction$217.0M
▸Indirect Field Costs$32.0M
Engineering$32.0M
▸Contingency & Escalation$81.0M
Project Contingency$29.0M
Process Contingency$52.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M
Holcim / Portland Cement Plant
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
76MW
CO₂ concentration
10.1%vol%
▸Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
▸Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M