Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
▸Direct Field Costs$385.9M
CO2 absorption$79.6M
Civil structural work$46.9M
General utility system$51.3M
CO2 Compression Equipment$43.3M
Flue Gas Conditioning$52.4M
Solvent regeneration$40.7M
Stack connection and modification$15.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary system$55.7M
▸Indirect Field Costs$57.1M
Construction preliminaries$34.7M
Engineering$10.4M
Mechanical completion, commissioning and testing$13.1M
Training$1.0M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction$27.0M
Report did not provide a further cost breakdown.
▸Owners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M
Linde Hydrogen Plant
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
18.3%mol%
▸Direct Field Costs$327.0M
Carbon Capture Plant$110.0M
Construction$217.0M
▸Indirect Field Costs$32.0M
Engineering$32.0M
▸Contingency & Escalation$81.0M
Project Contingency$29.0M
Process Contingency$52.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M
CRC / Elk Hills Power Plant
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
▸Direct Field Costs$444.7M
Concrete$51.1M
Structural Steel$19.1M
Capture Plant Equipment$104.7M
Utilities Equipment$58.5M
CO2 Compression Equipment$20.1M
Piping$69.4M
Electrical and Control Systems$47.2M
Scaffolding, Painting, Insulation$22.1M
Modularization$1.1M
Procurement, Taxes & Duties$26.0M
Pre-commisioning and Startup$5.8M
Earthwork & Civil$19.4M
▸Indirect Field Costs$206.3M
Indirect Field Costs$91.9M
Home Office$47.8M
EPC Fees$66.5M
▸Contingency & Escalation$96.0M
Escalation$39.0M
Contingency$57.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M