Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Rayburn Energy Station / Sherman Power Plant

Natural GasFEED· Bechtel· 2022-03-01Project page ↗Cost report ↗
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Fixed OpEx$9.5M
Maintenance material$4.5M
Operating labor$4.0M
Admin & support labor$1.0M
Variable OpEx$10.8M
Solvent & chemicals$1.5M
Steam & electricity$8.4M
Waste disposal$0.9M
Total Opex$20.3M

Finnish Market Pulp Mill / Capture of CO2 in the Kraft Recovery Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,478,700t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
23.5MW
CO₂ concentration
14.7%mol%
Fixed OpEx$14.1M
Property taxes & insurance$3.1M
Operating labor$1.3M
Maintenance labor$9.2M
Admin & support labor$0.5M
Variable OpEx$9.7M
Solvent & chemicals$3.2M
Electricity$6.0M
Waste disposal$0.5M
Total Opex$23.8M

Red Trail Energy Richardton Ethanol

Ethanol· Trimeric· 2019-11-20Project page ↗Cost report ↗
CO₂ captured
214,255t/yr
Capture efficiency
Utilization
95.9%
Parasitic load
MW
CO₂ concentration
99.9%mol%
Fixed OpEx
Report did not provide a further cost breakdown.
Variable OpEx
Report did not provide a further cost breakdown.
Total Opex