Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Rayburn Energy Station / Sherman Power Plant

Natural GasFEED· Bechtel· 2022-03-01Project page ↗Cost report ↗
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Direct Field Costs$385.9M
CO2 absorption$79.6M
Civil structural work$46.9M
General utility system$51.3M
CO2 Compression Equipment$43.3M
Flue Gas Conditioning$52.4M
Solvent regeneration$40.7M
Stack connection and modification$15.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary system$55.7M
Indirect Field Costs$57.1M
Construction preliminaries$34.7M
Engineering$10.4M
Mechanical completion, commissioning and testing$13.1M
Training$1.0M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction$27.0M
Report did not provide a further cost breakdown.
Owners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M

Peterhead Power Station (Aberdeenshire)

Natural GasFEED· Shell· Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$331.4M
Solvent Pumping and Conditioning$56.0M
Indirect Field Costs$89.7M
Indirect Field Costs$73.4M
Engineering$16.3M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Direct Field Costs$2.17B
Auxiliary power and fans$94.1M
Absorber$288.0M
Common facilities$327.5M
Carbon Capture Plant$1.45B
Switchyard$6.2M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.17B