Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Holcim / Ste. Genevieve Cement Plant

CementFEED· University of Illinois· 2024-08-29Project page ↗Cost report ↗
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
Fixed OpEx$59.9M
Maint. / property taxes / insurance$56.0M
Operating labor$3.9M
Variable OpEx$84.2M
Electricity$80.0M
Waste disposal$4.2M
Total Opex$144.1M

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Fixed OpEx$16.8M
Report did not provide a further cost breakdown.
Variable OpEx$43.9M
Report did not provide a further cost breakdown.
Total Opex$60.7M

Finnish Integrated Pulp and Board Mill / 400,000 adt/y production / Capture of CO2 in the Kraft Recovery Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,478,700t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
23.5MW
CO₂ concentration
14.7%mol%
Fixed OpEx$17.2M
Property taxes & insurance$3.5M
Operating labor$2.0M
Maintenance labor$10.6M
Admin & support labor$1.0M
Variable OpEx$18.1M
Solvent & chemicals$3.2M
Natural gas fuel cost$8.3M
Electricity$6.1M
Waste disposal$0.5M
Total Opex$35.3M