Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Holcim / Ste. Genevieve Cement Plant

CementFEED· University of Illinois· 2024-08-29Project page ↗Cost report ↗
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
Direct Field Costs$900.4M
Material Cost
Indirect Field Costs$517.7M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$250.5M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.0M
Financing Cost
Pre-production Cost
Inventory Capital
Total Capex$1.74B

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Direct Field Costs$520.0M
CO2 Compression Equipment
Indirect Field Costs$160.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$293.2M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$973.6M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
Civil structural work
Indirect Field Costs$754.3M
Indirect Field Costs
Contingency & Escalation$303.0M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B