Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

2 of 3 selectedClear selection46 reports
Comparing 2 reports — tab selection applies to every column.

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Report metadata
CurrencyUSD / $
Cost reference date2021
UncertaintyPlus or minus 15%
Report date2022-01-07

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Report metadata
CurrencyUSD / $
Cost reference date2018
UncertaintyAACE Class 4 (-30% / +50%)
Report date2023-08-15