Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Direct Field Costs$1.65B
Utilities Equipment
Indirect Field Costs$187.0M
Engineering
Contingency & Escalation$418.3M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$507.6M
Financing Cost
Pre-production Cost
Inventory Capital
Other's owners cost
Total Capex$3.19B

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Direct Field Costs$71.7M
Flue Gas Systems
Indirect Field Costs$6.7M
Engineering
Project Management
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$78.4M

Phillips 66 / Rodeo Refinery

Hydrogenpre-FEED· Phillips 66 Company· 2023-08-09Project page ↗Cost report ↗
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
MW
CO₂ concentration
18.0%vol%
Direct Field Costs$100.7M
Foundations
Indirect Field Costs$60.9M
Indirect Labor
Indirect Materials
Engineering
Project Development (FEL 2 and 3)
Contingency & Escalation$48.3M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$29.4M
Report did not provide a further cost breakdown.
Total Capex$239.4M