Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Cleveland Cliffs / Burns Harbor
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
21.9%vol%
▸Direct Field Costs$445.8M
Carbon Capture Island Equipment$116.6M
Steam and Power System Equipment$66.4M
Materials$190.1M
Labor$23.7M
Blast Furnace Gas Processing Equipment$48.1M
▸Indirect Field Costs$66.9M
EPC Fees$66.9M
▸Contingency & Escalation$67.5M
Contingency$67.5M
▸Interest During Construction$74.5M
Report did not provide a further cost breakdown.
▸Owners Cost$121.4M
Financing Cost$15.7M
Pre-production Cost$15.0M
Inventory Capital$3.7M
Other's owners cost$87.0M
Total Capex$776.1M
Prairie State Generating
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
—MW
CO₂ concentration
11.4%vol%
▸Direct Field Costs$1.89B
CO2 Capture System$150.7M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B
Finnish Integrated Pulp and Board Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
▸Direct Field Costs$385.8M
Lime Kiln: booster fan and ductwork$0.2M
Multi-fuel boiler: booster fan and ductwork$0.3M
Steam turbine island modifications$9.6M
Auxiliary boiler modifications$41.8M
Waste water treatment$4.8M
Common flue gas stack$1.1M
Direct Contact Cooler$5.2M
Amine absorber section$36.8M
Amine circulation system$3.5M
Stripper section$80.3M
CO2 Compression and dehydration$19.5M
Auxiliaries$1.2M
Other direct material cost$26.5M
Construction$102.9M
EPC and other costs$51.3M
Recovery Boiler: booster fan and ductwork$0.6M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$38.6M
Contingency$38.6M
▸Interest During Construction$62.9M
Report did not provide a further cost breakdown.
▸Owners Cost$45.5M
Report did not provide a further cost breakdown.
Total Capex$532.7M