Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Holcim / Portland Cement Plant
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
76MW
CO₂ concentration
10.1%vol%
▸Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
▸Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M
Linde Hydrogen Plant
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
18.3%mol%
▸Direct Field Costs$327.0M
Carbon Capture Plant$110.0M
Construction$217.0M
▸Indirect Field Costs$32.0M
Engineering$32.0M
▸Contingency & Escalation$81.0M
Project Contingency$29.0M
Process Contingency$52.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M
Mustang Station Power Plant
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
▸Direct Field Costs$384.1M
Solvent Pumping and Conditioning$56.0M
Absorber$37.0M
Wash Water System$33.9M
Buildings & Facilities$31.8M
Process Utilities$29.7M
CO2 Compression Equipment$24.2M
Flue Gas Systems$21.6M
Solvent Reclaiming$19.6M
Spare Parts, First Fills, Commodity Freight$18.1M
Stripper, CO2 Conditioning$17.4M
Steam Generation$15.2M
Solvent Heat Exchangers$9.5M
Solvent Storage$6.5M
E&I Infrastructure$63.5M
▸Indirect Field Costs$209.7M
Indirect Field Costs$93.1M
Contractor’s Profit$60.1M
Engineering$37.0M
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)$19.5M
▸Contingency & Escalation$104.6M
Contingency$104.6M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M