Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M

Finnish Market Pulp Mill / Capture of CO2 in the Lime Kiln only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
Direct Field Costs$52.7M
Steam turbine island modifications$6.6M
Waste water treatment$3.6M
Direct Contact Cooler$0.7M
Amine absorber section$5.0M
Amine circulation system$0.5M
Stripper section$11.0M
CO2 Compression and dehydration$1.3M
Auxiliaries$0.2M
Other direct material cost$3.6M
Construction$13.3M
EPC and other costs$5.6M
Multi-fuel boiler: booster fan and ductwork$0.2M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$5.3M
Contingency$5.3M
Interest During Construction$8.6M
Report did not provide a further cost breakdown.
Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.4M

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
Civil and Structural$157.7M
Piping and Ducting$219.2M
NGCC Base Modifications Equipment$23.0M
Exhaust Gas Recirculation System Equipment$60.4M
Gas Turbine Modifications Equipment$47.3M
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment$169.2M
CO2 Compression Equipment$60.9M
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment$27.2M
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCC$46.8M
Initial fill of CCS inventory (Solvent and Activated Carbon)'$29.9M
Labor$210.3M
Foundations$50.0M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency$192.4M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B