Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in both Kraft & Multi-boilers

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
Direct Field Costs$366.5M
Feedwater & Misc. Balance of Plant Equipment & Systems$180.5M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$36.7M
Contingency$36.7M
Interest During Construction$59.7M
Report did not provide a further cost breakdown.
Owners Cost$43.2M
Report did not provide a further cost breakdown.
Total Capex$506.0M

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Earthwork Associated with Carbon Capture$85.0M
Water Supply and Treatment$36.7M
Wastewater$5.0M
Drainage$0.3M
Power Supply$4.9M
Controls & Internet$0.3M
Owner Facilities$2.2M
Impurity Removal and CO2 conditioning$56.0M
Enclosures & Buildings$79.0M
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)$330.0M
Carbon Capture Plant$745.0M
Indirect Field Costs$61.5M
Project Management$19.9M
Limited Notice to Proceed$8.7M
Services$24.1M
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)$8.7M
Contingency & Escalation$470.0M
Owner's Cost Contingency$22.6M
EPC Contingency$356.3M
Escalation$4.2M
Regional Adjustment for Labor$87.0M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts$10.4M
License fee$10.0M
Insurance$6.6M
Startup$7.1M
Miscellaneous$37.1M
Total Capex$1.95B