Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Holcim / Portland Cement Plant
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
76MW
CO₂ concentration
10.1%vol%
▸Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
▸Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M
Southern Company / Plant Daniel
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
—
▸Direct Field Costs$515.2M
Construction – Including Labor, Materials, and Contracted Equipment$497.1M
Engineering-Procured Materials$18.1M
▸Indirect Field Costs$56.6M
Project Management$8.7M
Engineering – Including Construction and Startup Support$47.9M
▸Contingency & Escalation$126.3M
Contingency$126.3M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$54.1M
Front End Planning$4.5M
Startup$31.8M
Other's owners cost$17.8M
Total Capex$752.2M
Finnish Integrated Pulp and Board Mill / Capture of CO2 in both Kraft & Multi-boilers
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
▸Direct Field Costs$366.5M
Feedwater & Misc. Balance of Plant Equipment & Systems$180.5M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$36.7M
Contingency$36.7M
▸Interest During Construction$59.7M
Report did not provide a further cost breakdown.
▸Owners Cost$43.2M
Report did not provide a further cost breakdown.
Total Capex$506.0M