Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Direct Field Costs$489.9M
Construction$332.2M
Materials Cost$157.7M
Indirect Field Costs$37.5M
Engineering$37.5M
Contingency & Escalation$86.6M
Project Contingency$46.0M
Process Contingency$40.6M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Direct Field Costs$384.1M
Solvent Pumping and Conditioning$56.0M
Absorber$37.0M
Wash Water System$33.9M
Buildings & Facilities$31.8M
Process Utilities$29.7M
CO2 Compression Equipment$24.2M
Flue Gas Systems$21.6M
Solvent Reclaiming$19.6M
Spare Parts, First Fills, Commodity Freight$18.1M
Stripper, CO2 Conditioning$17.4M
Steam Generation$15.2M
Solvent Heat Exchangers$9.5M
Solvent Storage$6.5M
E&I Infrastructure$63.5M
Indirect Field Costs$209.7M
Indirect Field Costs$93.1M
Contractor’s Profit$60.1M
Engineering$37.0M
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)$19.5M
Contingency & Escalation$104.6M
Contingency$104.6M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$91.8M
CO2 Compression Equipment$28.2M
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies$60.2M
Dehydration$2.4M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$91.8M