Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Direct Field Costs$489.9M
Construction$332.2M
Materials Cost$157.7M
Indirect Field Costs$37.5M
Engineering$37.5M
Contingency & Escalation$86.6M
Project Contingency$46.0M
Process Contingency$40.6M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Direct Field Costs$575.3M
Module Shop Fabrication$16.3M
Site Installation$23.9M
Absorber, cooling system, compression, vessels, pumps$230.3M
Piping materials, ductwork, racks$59.3M
Civil materials, concrete, site materials$49.7M
Structural steel materials$19.7M
Electrical materials and equipment$39.6M
Instruments and automation hardware$8.9M
Insulation materials$1.0M
Paint and coatings$0.1M
Freight, heavy lift, hauling$18.0M
All field installation labor$149.1M
Major Equipment$31.6M
Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead$54.3M
EPC engineering and detailed design$50.6M
Contingency & Escalation$145.5M
Contingency$104.0M
Escalation$41.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$23.6M
Owner's cost$23.6M
Total Capex$849.3M

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
Civil and Structural$157.7M
Piping and Ducting$219.2M
NGCC Base Modifications Equipment$23.0M
Exhaust Gas Recirculation System Equipment$60.4M
Gas Turbine Modifications Equipment$47.3M
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment$169.2M
CO2 Compression Equipment$60.9M
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment$27.2M
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCC$46.8M
Initial fill of CCS inventory (Solvent and Activated Carbon)'$29.9M
Labor$210.3M
Foundations$50.0M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency$192.4M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B