Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Membrane Technology and Research (MTR)· 2022-06-03Project page ↗Cost report ↗
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Direct Field Costs$262.6M
Material$50.1M
Construction equipment$9.0M
Raw Material Relocation$12.3M
Labor$32.9M
Process equipment$121.6M
Subcontract$35.6M
Indirect Field Costs$123.7M
Project Indirects$53.7M
Construction Indirect$70.0M
Contingency & Escalation$123.9M
Contingency$57.9M
Escalation$65.9M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$510.2M

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEED· Dastur International· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
79MW
CO₂ concentration
21.9%vol%
Direct Field Costs$445.8M
Carbon Capture Island Equipment$116.6M
Steam and Power System Equipment$66.4M
Materials$190.1M
Labor$23.7M
Blast Furnace Gas Processing Equipment$48.1M
Indirect Field Costs$66.9M
EPC Fees$66.9M
Contingency & Escalation$67.5M
Contingency$67.5M
Interest During Construction$74.5M
Report did not provide a further cost breakdown.
Owners Cost$121.4M
Financing Cost$15.7M
Pre-production Cost$15.0M
Inventory Capital$3.7M
Other's owners cost$87.0M
Total Capex$776.1M

Finnish Market Pulp Mill / Capture of CO2 in the Kraft Recovery Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,478,700t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
23.5MW
CO₂ concentration
14.7%mol%
Direct Field Costs$278.2M
Steam turbine island modifications$6.6M
Waste waster treatment modifications$4.3M
Direct Contact Cooler$4.5M
Amine absorber section$31.8M
Amine circulation system$3.0M
Stripper section$69.3M
CO2 Compression and dehydration$8.4M
Auxiliaries$1.0M
Other direct material cost$22.9M
Construction$83.8M
EPC and other costs$41.8M
Recovery Boiler Modifications: booster fan and ductwork$0.6M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$27.8M
Contingency$27.8M
Interest During Construction$45.2M
Report did not provide a further cost breakdown.
Owners Cost$31.3M
Report did not provide a further cost breakdown.
Total Capex$382.6M