Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Membrane Technology and Research (MTR)· 2022-06-03Project page ↗Cost report ↗
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Direct Field Costs$262.6M
Pre-commisioning and Startup
Indirect Field Costs$123.7M
Project Indirects
Construction Indirect
Contingency & Escalation$123.9M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$510.2M

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Direct Field Costs$489.9M
Procurement, Taxes & Duties
Indirect Field Costs$37.5M
Engineering
Contingency & Escalation$86.6M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$89.1M
CO2 Compression Equipment
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$89.1M