Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Membrane Technology and Research (MTR)· 2022-06-03Project page ↗Cost report ↗
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Direct Field Costs$262.6M
Pre-commisioning and Startup
Indirect Field Costs$123.7M
Project Indirects
Construction Indirect
Contingency & Escalation$123.9M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$510.2M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
Direct Field Costs$385.8M
Cooling Water System
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$38.6M
Contingency
Interest During Construction$62.9M
Report did not provide a further cost breakdown.
Owners Cost$45.5M
Report did not provide a further cost breakdown.
Total Capex$532.7M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
Civil structural work
Indirect Field Costs$754.3M
Indirect Field Costs
Contingency & Escalation$303.0M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B