Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Phillips 66 / Rodeo Refinery

Hydrogenpre-FEED· Phillips 66 Company· 2023-08-09Project page ↗Cost report ↗
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
MW
CO₂ concentration
18.0%vol%
Direct Field Costs$100.7M
Major Equipment$25.9M
Site Improvements$0.3M
Concrete$0.7M
Structural Steel$3.0M
Ductwork, Insulation, Piping$6.0M
Instrumentation and Electrical$7.9M
Painting$0.2M
Freight$2.5M
Design Allowance$6.2M
Labor$48.1M
Indirect Field Costs$60.9M
Indirect Labor$15.9M
Indirect Materials$12.5M
Engineering$22.7M
Project Development (FEL 2 and 3)$9.7M
Contingency & Escalation$48.3M
Contingency$39.5M
Escalation$8.8M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$29.4M
Report did not provide a further cost breakdown.
Total Capex$239.4M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
4,200,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$153.0M
CO2 Compression Equipment$47.6M
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies$102.0M
Dehydration$3.4M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$153.0M

Scottish Power / Longannet Power Station

Natural GasFEED· ScottishPower· 2011-04-01Project page ↗
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$509.8M
Carbon Capture Process$228.1M
Compression and Conditioning$47.2M
Balance of Plant and Utilities$119.7M
Steam and Power Supply$114.8M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$98.5M
Contingency$98.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M