Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Phillips 66 / Rodeo Refinery

Hydrogenpre-FEED· Phillips 66 Company· 2023-08-09Project page ↗Cost report ↗
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
MW
CO₂ concentration
18.0%vol%
Report metadata
CurrencyUSD / $
Cost reference dateQ4 2022
UncertaintyFEL 2 (+25%/-15%)
Report date2023-08-09

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Report metadata
CurrencyUSD / $
Cost reference dateNovemeber 2023
UncertaintyAACE Class 3 (-20% / +30%)
Report date2024-08-06

Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Multi-fuel Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
270,658t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
4.4MW
CO₂ concentration
16.8%mol%
Report metadata
CurrencyUSD / $
Cost reference dateQ2 2015
UncertaintyPlus or minus 35%
Report date2016-12-01