Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Linde Hydrogen Plant

Hydrogenpre-FEED· Praxair· 2022-11-03Project page ↗Cost report ↗
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
MW
CO₂ concentration
18.3%mol%
Direct Field Costs$327.0M
Civil and Structural$157.7M
Indirect Field Costs$32.0M
Engineering$32.0M
Contingency & Escalation$81.0M
Project Contingency$29.0M
Process Contingency$52.0M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Direct Field Costs$489.9M
Procurement, Taxes & Duties$26.0M
Indirect Field Costs$37.5M
Engineering$37.5M
Contingency & Escalation$86.6M
Project Contingency$46.0M
Process Contingency$40.6M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Direct Field Costs$384.1M
Earthwork & Civil$19.4M
Indirect Field Costs$209.7M
Indirect Field Costs$93.1M
Contractor’s Profit$60.1M
Engineering$37.0M
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)$19.5M
Contingency & Escalation$104.6M
Contingency$104.6M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M