Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Linde Hydrogen Plant

Hydrogenpre-FEED· Praxair· 2022-11-03Project page ↗Cost report ↗
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
MW
CO₂ concentration
18.3%mol%
Direct Field Costs$327.0M
Carbon Capture Plant$110.0M
Construction$217.0M
Indirect Field Costs$32.0M
Engineering$32.0M
Contingency & Escalation$81.0M
Project Contingency$29.0M
Process Contingency$52.0M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Direct Field Costs$71.7M
Flue Gas Systems$21.6M
Indirect Field Costs$6.7M
Engineering$2.2M
Project Management$4.4M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$78.4M

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M