Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Finnish Market Pulp Mill / Capture of CO2 in the Kraft Recovery Boiler only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,478,700t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
23.5MW
CO₂ concentration
14.7%mol%
▸Direct Field Costs$278.2M
Steam turbine island modifications$6.6M
Waste waster treatment modifications$4.3M
Direct Contact Cooler$4.5M
Amine absorber section$31.8M
Amine circulation system$3.0M
Stripper section$69.3M
CO2 Compression and dehydration$8.4M
Auxiliaries$1.0M
Other direct material cost$22.9M
Construction$83.8M
EPC and other costs$41.8M
Recovery Boiler Modifications: booster fan and ductwork$0.6M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$27.8M
Contingency$27.8M
▸Interest During Construction$45.2M
Report did not provide a further cost breakdown.
▸Owners Cost$31.3M
Report did not provide a further cost breakdown.
Total Capex$382.6M
Nutrien Redwater Nitrogen Operations
CO₂ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
7.0%mol%
▸Direct Field Costs$520.0M
CO2 Compression Equipment$24.2M
▸Indirect Field Costs$160.3M
Report did not provide a further cost breakdown.
▸Contingency & Escalation$293.2M
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$973.6M
Finnish Market Pulp Mill / Capture of CO2 in the Lime Kiln only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
▸Direct Field Costs$52.7M
Steam turbine island modifications$6.6M
Waste water treatment$3.6M
Direct Contact Cooler$0.7M
Amine absorber section$5.0M
Amine circulation system$0.5M
Stripper section$11.0M
CO2 Compression and dehydration$1.3M
Auxiliaries$0.2M
Other direct material cost$3.6M
Construction$13.3M
EPC and other costs$5.6M
Multi-fuel boiler: booster fan and ductwork$0.2M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$5.3M
Contingency$5.3M
▸Interest During Construction$8.6M
Report did not provide a further cost breakdown.
▸Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.4M