Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
Civil structural work
Indirect Field Costs$754.3M
Indirect Field Costs
Contingency & Escalation$303.0M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B

Holcim / Ste. Genevieve Cement Plant

CementFEED· University of Illinois· 2024-08-29Project page ↗Cost report ↗
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
Direct Field Costs$900.4M
Material Cost
Indirect Field Costs$517.7M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$250.5M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.0M
Financing Cost
Pre-production Cost
Inventory Capital
Total Capex$1.74B

Finnish Market Pulp Mill / Capture of CO2 in the Lime Kiln only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
Direct Field Costs$52.7M
Owner Facilities
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$5.3M
Contingency
Interest During Construction$8.6M
Report did not provide a further cost breakdown.
Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.4M