Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Finnish Market Pulp Mill / Capture of CO2 in both Kraft & Multi-boilers
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
▸Direct Field Costs$309.2M
Multi-fuel boiler: booster fan and ductwork$0.3M
Steam turbine island modifications$6.6M
Waste water treatment$4.4M
Common flue gas stack$1.1M
Direct Contact Cooler$5.0M
Amine absorber section$35.3M
Amine circulation system$3.3M
Stripper section$77.0M
CO2 Compression and dehydration$9.3M
Auxiliaries$1.2M
Other direct material cost$25.4M
Construction$93.1M
EPC and other costs$45.4M
Recovery Boiler: booster fan and ductwor$0.6M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$30.9M
Contingency$30.9M
▸Interest During Construction$50.2M
Report did not provide a further cost breakdown.
▸Owners Cost$34.9M
Report did not provide a further cost breakdown.
Total Capex$425.2M
Holcim / Ste. Genevieve Cement Plant
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
▸Direct Field Costs$900.4M
Accessory Electric Plant$62.8M
Cooling Water System$39.2M
Buildings & Structure$54.9M
Improvements to Site$23.5M
CO2 Compression Equipment$31.4M
Flue Gas Cleanup$39.2M
Ductwork and Stack$62.8M
Labor$115.5M
Instrumentation and Control$7.8M
Carbon Capture Plant$282.6M
Feedwater & Misc. Balance of Plant Equipment & Systems$180.5M
▸Indirect Field Costs$517.7M
Engineering, Construction Management, Home Office and Fee$517.7M
▸Contingency & Escalation$250.5M
Contingency$250.5M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$71.0M
Financing Cost$50.7M
Pre-production Cost$9.5M
Inventory Capital$10.8M
Total Capex$1.74B
Scottish Power / Longannet Power Station
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
▸Direct Field Costs$509.8M
Carbon Capture Process$228.1M
Compression and Conditioning$47.2M
Balance of Plant and Utilities$119.7M
Steam and Power Supply$114.8M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$98.5M
Contingency$98.5M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M