Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Finnish Market Pulp Mill / Capture of CO2 in both Kraft & Multi-boilers

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
Direct Field Costs$309.2M
Impurity Removal and CO2 conditioning
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$30.9M
Contingency
Interest During Construction$50.2M
Report did not provide a further cost breakdown.
Owners Cost$34.9M
Report did not provide a further cost breakdown.
Total Capex$425.2M

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEED· Dastur International· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
79MW
CO₂ concentration
21.9%vol%
Direct Field Costs$445.8M
Scaffolding, Painting, Insulation
Indirect Field Costs$66.9M
EPC Fees
Contingency & Escalation$67.5M
Contingency
Interest During Construction$74.5M
Report did not provide a further cost breakdown.
Owners Cost$121.4M
Financing Cost
Pre-production Cost
Inventory Capital
Other's owners cost
Total Capex$776.1M

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Cooling Water System
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B