Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Multi-fuel Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
270,658t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
4.4MW
CO₂ concentration
16.8%mol%
Direct Field Costs$83.0M
Construction – Including Labor, Materials, and Contracted Equipment
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$8.3M
Contingency
Interest During Construction$13.5M
Report did not provide a further cost breakdown.
Owners Cost$9.2M
Report did not provide a further cost breakdown.
Total Capex$114.0M

Prairie State Generating

CoalFEED· University of Illinois· 2022-09-03Project page ↗Cost report ↗
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
11.4%vol%
Direct Field Costs$1.89B
CO2 Capture System
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Direct Field Costs$575.3M
Solvent Reclaiming
Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead
EPC engineering and detailed design
Contingency & Escalation$145.5M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$23.6M
Owner's cost
Total Capex$849.3M