Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Lime Kiln only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
▸Direct Field Costs$52.8M
Steam turbine island modifications$6.4M
Waste water treatment$4.0M
Direct Contact Cooler$0.7M
Amine absorber section$5.0M
Amine circulation system$0.5M
Stripper section$11.0M
CO2 Compression and dehydration$1.3M
Auxiliaries$0.2M
Other direct material cost$3.6M
Construction$13.3M
EPC and other costs$5.6M
Lime Kiln: booster fan and ductwork$0.2M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$5.3M
Contingency$5.3M
▸Interest During Construction$8.6M
Report did not provide a further cost breakdown.
▸Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.5M
Linde / Port Arthur Facility
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
—MW
CO₂ concentration
16.2%mol%
▸Direct Field Costs$489.9M
Construction$332.2M
Materials Cost$157.7M
▸Indirect Field Costs$37.5M
Engineering$37.5M
▸Contingency & Escalation$86.6M
Project Contingency$46.0M
Process Contingency$40.6M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M
Technology Centre Mongstad
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
▸Direct Field Costs$1.65B
Coal & Sorbent Prep & Feed Equipment$13.5M
Feedwater & Misc. Balance of Plant Systems Equipment$50.1M
Pulverized coal-fired boiler Equipment$297.9M
Flue Gas Cleanup Equipment$81.3M
CO2 Capture System Equipment$154.4M
CO2 Compression and Purification Equipment$80.5M
HRSG, Ducting & Stack Equipment$8.7M
Steam Turbine Generator Equipment$131.5M
Cooling Water System Equipment$34.9M
Ash/Spent Sorbent Handling System Equipment$5.0M
Accessory Electric Plant Equipment$34.0M
Instrumentation & Control Equipment$12.6M
Improvements to Site Equipment$2.6M
Materials$66.3M
Labor$626.7M
Coal & Sorbent Handling Equipment$48.5M
▸Indirect Field Costs$187.0M
Engineering$187.0M
▸Contingency & Escalation$418.3M
Project Contingency$417.5M
Process Contingency$0.8M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$507.6M
Financing Cost$60.9M
Pre-production Cost$66.8M
Inventory Capital$37.9M
Other's owners cost$342.0M
Total Capex$3.19B