Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Finnish Integrated Pulp and Board Mill / Capture of CO2 in both Kraft Boiler & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,675,922t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
26.9MW
CO₂ concentration
15.5%mol%
Direct Field Costs$348.1M
Accessory Electric Plant
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$34.8M
Contingency
Interest During Construction$56.7M
Report did not provide a further cost breakdown.
Owners Cost$41.0M
Report did not provide a further cost breakdown.
Total Capex$480.6M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2023-05-03Project page ↗Cost report ↗
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
Direct Field Costs$415.7M
General utility system
Indirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$76.7M
Project Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$19.9M
Pre-production Cost
Inventory Capital
Total Capex$595.5M

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Direct Field Costs$489.9M
Procurement, Taxes & Duties
Indirect Field Costs$37.5M
Engineering
Contingency & Escalation$86.6M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M