Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Calpine / Deer Park Energy Center
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
▸Direct Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systems$15.1M
Combustion Turbine & Accessories$31.0M
Steam Turbine & Accessories$18.3M
Cooling Water System$7.5M
Accessory Electric Plant$6.7M
Instrumentation & Control$9.4M
Improvements to Site$0.6M
Material Cost$52.9M
CO2 Capture System$150.7M
Direct Labor$96.8M
HRSG, Ductwork, & Stack$26.8M
▸Indirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Fee$83.1M
▸Contingency & Escalation$76.7M
Project Contingency$76.7M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$19.9M
Pre-production Cost$16.7M
Inventory Capital$3.2M
Total Capex$595.5M
Finnish Market Pulp Mill / Capture of CO2 in the Multi-fuel Boiler only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
270,658t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
4.4MW
CO₂ concentration
16.8%mol%
▸Direct Field Costs$82.9M
Steam turbine island modifications$6.6M
Waste water treatment$3.8M
Direct Contact Cooler$1.1M
Amine absorber section$8.6M
Amine circulation system$0.8M
Stripper section$18.8M
CO2 Compression and dehydration$2.3M
Auxiliaries$0.3M
Other direct material cost$6.1M
Construction$22.7M
EPC and other costs$11.3M
Multi-fuel boiler: booster fan and ductwork$0.3M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$8.3M
Contingency$8.3M
▸Interest During Construction$13.5M
Report did not provide a further cost breakdown.
▸Owners Cost$9.2M
Report did not provide a further cost breakdown.
Total Capex$113.8M
Finnish Market Pulp Mill / Capture of CO2 in the Lime Kiln only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
▸Direct Field Costs$52.7M
Steam turbine island modifications$6.6M
Waste water treatment$3.6M
Direct Contact Cooler$0.7M
Amine absorber section$5.0M
Amine circulation system$0.5M
Stripper section$11.0M
CO2 Compression and dehydration$1.3M
Auxiliaries$0.2M
Other direct material cost$3.6M
Construction$13.3M
EPC and other costs$5.6M
Multi-fuel boiler: booster fan and ductwork$0.2M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$5.3M
Contingency$5.3M
▸Interest During Construction$8.6M
Report did not provide a further cost breakdown.
▸Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.4M