Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Calpine / Deer Park Energy Center
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
▸Direct Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systems$15.1M
Combustion Turbine & Accessories$31.0M
Steam Turbine & Accessories$18.3M
Cooling Water System$7.5M
Accessory Electric Plant$6.7M
Instrumentation & Control$9.4M
Improvements to Site$0.6M
Material Cost$52.9M
CO2 Capture System$150.7M
Direct Labor$96.8M
HRSG, Ductwork, & Stack$26.8M
▸Indirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Fee$83.1M
▸Contingency & Escalation$76.7M
Project Contingency$76.7M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$19.9M
Pre-production Cost$16.7M
Inventory Capital$3.2M
Total Capex$595.5M
Devon Energy / Jackfish-1 Oil Sands
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
8.6%mol%
▸Direct Field Costs$71.7M
Module Shop Fabrication$16.3M
Site Installation$22.9M
Major Equipment$31.6M
▸Indirect Field Costs$6.7M
Engineering$2.2M
Project Management$4.4M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$78.4M
Holcim / Portland Cement Plant
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
76MW
CO₂ concentration
10.1%vol%
▸Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
▸Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M