Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Finnish Integrated Pulp and Board Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
▸Direct Field Costs$385.8M
Cooling Water System$39.2M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$38.6M
Contingency$38.6M
▸Interest During Construction$62.9M
Report did not provide a further cost breakdown.
▸Owners Cost$45.5M
Report did not provide a further cost breakdown.
Total Capex$532.7M
Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Multi-fuel Boiler only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
270,658t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
4.4MW
CO₂ concentration
16.8%mol%
▸Direct Field Costs$83.0M
Construction – Including Labor, Materials, and Contracted Equipment$497.1M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$8.3M
Contingency$8.3M
▸Interest During Construction$13.5M
Report did not provide a further cost breakdown.
▸Owners Cost$9.2M
Report did not provide a further cost breakdown.
Total Capex$114.0M
Phillips 66 / Rodeo Refinery
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
—MW
CO₂ concentration
18.0%vol%
▸Direct Field Costs$100.7M
Major Equipment$25.9M
Site Improvements$0.3M
Concrete$0.7M
Structural Steel$3.0M
Ductwork, Insulation, Piping$6.0M
Instrumentation and Electrical$7.9M
Painting$0.2M
Freight$2.5M
Design Allowance$6.2M
Labor$48.1M
▸Indirect Field Costs$60.9M
Indirect Labor$15.9M
Indirect Materials$12.5M
Engineering$22.7M
Project Development (FEL 2 and 3)$9.7M
▸Contingency & Escalation$48.3M
Contingency$39.5M
Escalation$8.8M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$29.4M
Report did not provide a further cost breakdown.
Total Capex$239.4M