Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Red Trail Energy Richardton Ethanol
CO₂ captured
214,255t/yr
Capture efficiency
—
Utilization
95.9%
Parasitic load
—MW
CO₂ concentration
99.9%mol%
▸Direct Field Costs$19.8M
Buldings & Structure$54.9M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$19.8M
Finnish Integrated Pulp and Board Mill / 400,000 adt/y production / Capture of CO2 in the Kraft Recovery Boiler only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,478,700t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
23.5MW
CO₂ concentration
14.7%mol%
▸Direct Field Costs$321.6M
Engineering-Procured Materials$18.1M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$32.2M
Contingency$32.2M
▸Interest During Construction$52.4M
Report did not provide a further cost breakdown.
▸Owners Cost$37.9M
Report did not provide a further cost breakdown.
Total Capex$444.0M
CRC / Elk Hills Power Plant
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
▸Direct Field Costs$444.7M
Concrete$51.1M
Structural Steel$19.1M
Capture Plant Equipment$104.7M
Utilities Equipment$58.5M
CO2 Compression Equipment$20.1M
Piping$69.4M
Electrical and Control Systems$47.2M
Scaffolding, Painting, Insulation$22.1M
Modularization$1.1M
Procurement, Taxes & Duties$26.0M
Pre-commisioning and Startup$5.8M
Earthwork & Civil$19.4M
▸Indirect Field Costs$206.3M
Indirect Field Costs$91.9M
Home Office$47.8M
EPC Fees$66.5M
▸Contingency & Escalation$96.0M
Escalation$39.0M
Contingency$57.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M