Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Red Trail Energy Richardton Ethanol

Ethanol· Trimeric· 2019-11-20Project page ↗Cost report ↗
CO₂ captured
214,255t/yr
Capture efficiency
Utilization
95.9%
Parasitic load
MW
CO₂ concentration
99.9%mol%
Direct Field Costs$19.8M
Installation$6.3M
Storage Tank$2.6M
Freight Costs$0.2M
CO2 Compression Equipment$10.7M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$19.8M

Prairie State Generating

CoalFEED· University of Illinois· 2022-09-03Project page ↗Cost report ↗
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
11.4%vol%
Direct Field Costs$1.89B
CO2 Capture System$150.7M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M