Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$35.7M
CO2 Compression Equipment$10.4M
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies$23.8M
Dehydration$1.5M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$35.7M

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Direct Field Costs$575.3M
Module Shop Fabrication$16.3M
Site Installation$23.9M
Absorber, cooling system, compression, vessels, pumps$230.3M
Piping materials, ductwork, racks$59.3M
Civil materials, concrete, site materials$49.7M
Structural steel materials$19.7M
Electrical materials and equipment$39.6M
Instruments and automation hardware$8.9M
Insulation materials$1.0M
Paint and coatings$0.1M
Freight, heavy lift, hauling$18.0M
All field installation labor$149.1M
Major Equipment$31.6M
Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead$54.3M
EPC engineering and detailed design$50.6M
Contingency & Escalation$145.5M
Contingency$104.0M
Escalation$41.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$23.6M
Owner's cost$23.6M
Total Capex$849.3M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
CO2 Technology Costs$59.2M
Indirect Field Costs$754.3M
Indirect Field Costs$754.3M
Contingency & Escalation$303.0M
Contingency$303.0M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B