Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$89.1M
CO2 Compression Equipment
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$89.1M

Phillips 66 / Rodeo Refinery

Hydrogenpre-FEED· Phillips 66 Company· 2023-08-09Project page ↗Cost report ↗
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
MW
CO₂ concentration
18.0%vol%
Direct Field Costs$100.7M
Foundations
Indirect Field Costs$60.9M
Indirect Labor
Indirect Materials
Engineering
Project Development (FEL 2 and 3)
Contingency & Escalation$48.3M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$29.4M
Report did not provide a further cost breakdown.
Total Capex$239.4M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in both Kraft & Multi-boilers

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
Direct Field Costs$366.5M
Feedwater & Misc. Balance of Plant Equipment & Systems
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$36.7M
Contingency
Interest During Construction$59.7M
Report did not provide a further cost breakdown.
Owners Cost$43.2M
Report did not provide a further cost breakdown.
Total Capex$506.0M