Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$89.7M
Flue Gas Cleanup
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$89.7M

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Direct Field Costs$71.7M
Flue Gas Systems
Indirect Field Costs$6.7M
Engineering
Project Management
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$78.4M

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Direct Field Costs$1.09B
Process Utilities
Indirect Field Costs$337.8M
Report did not provide a further cost breakdown.
Contingency & Escalation$614.9M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.04B