Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Fixed OpEx$2.0M
Maintenance material$1.4M
Operating labor$0.7M
Variable OpEx$13.1M
Dehydration$0.6M
Electricity$12.5M
Total Opex$15.1M

CEMEX / Balcones Cement Plant

Cementpre-FEED· Membrane Technology and Research (MTR)· 2022-06-03Project page ↗Cost report ↗
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Fixed OpEx$6.2M
Maintenance material$2.3M
Operating labor$2.3M
Maintenance labor$1.6M
Variable OpEx$27.9M
Solvent & chemicals$2.7M
Electricity$25.1M
Total Opex$34.0M

Finnish Market Pulp Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
Fixed OpEx$16.2M
Property taxes & insurance$3.6M
Operating labor$1.3M
Maintenance labor$10.8M
Admin & support labor$0.5M
Variable OpEx$12.3M
Solvent & chemicals$4.2M
Electricity$7.4M
Waste disposal$0.7M
Total Opex$28.5M