Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Peterhead Power Station (Aberdeenshire)

Natural GasFEED· Shell· Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$331.4M
Solvent Pumping and Conditioning
Indirect Field Costs$89.7M
Indirect Field Costs
Engineering
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$91.8M
Ductwork and Stack
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$91.8M

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Cooling Water System
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B