Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection47 reports
Comparing 3 reports — tab selection applies to every column.

Peterhead Power Station (Aberdeenshire)

Natural GasFEED· Shell· Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$331.4M
Water System$13.8M
CO2 Compression Equipment$37.7M
Construction$119.6M
Carbon Capture Plant$159.6M
Electrical and Instrumentation / E&I$0.8M
Indirect Field Costs$89.7M
Indirect Field Costs$73.4M
Engineering$16.3M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M

Quest CCS — Scotford Upgrader

Bitumen upgrading — hydrogen productionFEED· Shell· 2021-01-01Project page ↗Cost report ↗
CO₂ captured
1,200,000t/yr
Capture efficiency
80.0%
Utilization
99.0%
Parasitic load
MW
CO₂ concentration
15.0%vol%
Direct Field Costs$483.8M
Construction & Commissioning$372.8M
Capture Facility Components & Procurement$110.9M
Indirect Field Costs$183.0M
FEED and Detailed Engineering$183.0M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$666.7M

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Direct Field Costs$520.0M
CO2 Compression Equipment$24.2M
Indirect Field Costs$160.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$293.2M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$973.6M