Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Peterhead Power Station (Aberdeenshire)

Natural GasFEED· Shell· Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Report metadata
CurrencyGBP / £
Cost reference date2015-12-01 00:00:00
Uncertainty(+15% / -10%)
Report date

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Report metadata
CurrencyUSD / $
Cost reference date2021
UncertaintyAACE Class 3 (-20% / +30%)
Report date2023-03-01

Linde Hydrogen Plant

Hydrogenpre-FEED· Praxair· 2022-11-03Project page ↗Cost report ↗
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
MW
CO₂ concentration
18.3%mol%
Report metadata
CurrencyUSD / $
Cost reference dateNot Available
UncertaintyPlus or minus 20%
Report date2022-11-03