Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
CRC / Elk Hills Power Plant
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
▸Direct Field Costs$444.7M
Concrete$51.1M
Structural Steel$19.1M
Capture Plant Equipment$104.7M
Utilities Equipment$58.5M
CO2 Compression Equipment$20.1M
Piping$69.4M
Electrical and Control Systems$47.2M
Scaffolding, Painting, Insulation$22.1M
Modularization$1.1M
Procurement, Taxes & Duties$26.0M
Pre-commisioning and Startup$5.8M
Earthwork & Civil$19.4M
▸Indirect Field Costs$206.3M
Indirect Field Costs$91.9M
Home Office$47.8M
EPC Fees$66.5M
▸Contingency & Escalation$96.0M
Escalation$39.0M
Contingency$57.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M
Linde / Port Arthur Facility
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
—MW
CO₂ concentration
16.2%mol%
▸Direct Field Costs$489.9M
Construction$332.2M
Materials Cost$157.7M
▸Indirect Field Costs$37.5M
Engineering$37.5M
▸Contingency & Escalation$86.6M
Project Contingency$46.0M
Process Contingency$40.6M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M
CEMEX / Balcones Cement Plant
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
▸Direct Field Costs$262.6M
Material$50.1M
Construction equipment$9.0M
Raw Material Relocation$12.3M
Labor$32.9M
Process equipment$121.6M
Subcontract$35.6M
▸Indirect Field Costs$123.7M
Project Indirects$53.7M
Construction Indirect$70.0M
▸Contingency & Escalation$123.9M
Contingency$57.9M
Escalation$65.9M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$510.2M