Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
CRC / Elk Hills Power Plant
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
▸Direct Field Costs$444.7M
Concrete$51.1M
Structural Steel$19.1M
Capture Plant Equipment$104.7M
Utilities Equipment$58.5M
CO2 Compression Equipment$20.1M
Piping$69.4M
Electrical and Control Systems$47.2M
Scaffolding, Painting, Insulation$22.1M
Modularization$1.1M
Procurement, Taxes & Duties$26.0M
Pre-commisioning and Startup$5.8M
Earthwork & Civil$19.4M
▸Indirect Field Costs$206.3M
Indirect Field Costs$91.9M
Home Office$47.8M
EPC Fees$66.5M
▸Contingency & Escalation$96.0M
Escalation$39.0M
Contingency$57.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M
Linde Hydrogen Plant
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
18.3%mol%
▸Direct Field Costs$327.0M
Carbon Capture Plant$110.0M
Construction$217.0M
▸Indirect Field Costs$32.0M
Engineering$32.0M
▸Contingency & Escalation$81.0M
Project Contingency$29.0M
Process Contingency$52.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M
Cleveland Cliffs / Burns Harbor
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
21.9%vol%
▸Direct Field Costs$445.8M
Carbon Capture Island Equipment$116.6M
Steam and Power System Equipment$66.4M
Materials$190.1M
Labor$23.7M
Blast Furnace Gas Processing Equipment$48.1M
▸Indirect Field Costs$66.9M
EPC Fees$66.9M
▸Contingency & Escalation$67.5M
Contingency$67.5M
▸Interest During Construction$74.5M
Report did not provide a further cost breakdown.
▸Owners Cost$121.4M
Financing Cost$15.7M
Pre-production Cost$15.0M
Inventory Capital$3.7M
Other's owners cost$87.0M
Total Capex$776.1M