Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CRC / Elk Hills Power Plant

Natural GasFEED· Electric Power Research Institute (EPRI)· 2020-09-01Project page ↗Cost report ↗
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
Direct Field Costs$444.7M
Solvent regeneration
Indirect Field Costs$206.3M
Indirect Field Costs
Home Office
EPC Fees
Contingency & Escalation$96.0M
Escalation
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
4,200,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$158.7M
E&I Infrastructure
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$158.7M

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Direct Field Costs$384.1M
Earthwork & Civil
Indirect Field Costs$209.7M
Indirect Field Costs
Contractor’s Profit
Engineering
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$104.6M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M