Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CLECO / Brame Energy Center Madison 3 Unit

CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
MW
CO₂ concentration
14.1%vol%
Direct Field Costs$667.2M
Absorber$37.0M
Indirect Field Costs$509.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$120.7M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.30B

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Direct Field Costs$575.3M
Solvent Reclaiming$19.6M
Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead$54.3M
EPC engineering and detailed design$50.6M
Contingency & Escalation$145.5M
Contingency$104.0M
Escalation$41.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$23.6M
Owner's cost$23.6M
Total Capex$849.3M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$89.1M
CO2 Compression Equipment$31.4M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$89.1M