Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Scottish Power / Longannet Power Station

Natural GasFEED· ScottishPower· 2011-04-01Project page ↗
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$509.8M
Carbon Capture Process$228.1M
Compression and Conditioning$47.2M
Balance of Plant and Utilities$119.7M
Steam and Power Supply$114.8M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$98.5M
Contingency$98.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
CO2 Technology Costs$59.2M
Indirect Field Costs$754.3M
Indirect Field Costs$754.3M
Contingency & Escalation$303.0M
Contingency$303.0M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B

Holcim / Ste. Genevieve Cement Plant

CementFEED· University of Illinois· 2024-08-29Project page ↗Cost report ↗
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
Direct Field Costs$900.4M
Accessory Electric Plant$62.8M
Cooling Water System$39.2M
Buildings & Structure$54.9M
Improvements to Site$23.5M
CO2 Compression Equipment$31.4M
Flue Gas Cleanup$39.2M
Ductwork and Stack$62.8M
Labor$115.5M
Instrumentation and Control$7.8M
Carbon Capture Plant$282.6M
Feedwater & Misc. Balance of Plant Equipment & Systems$180.5M
Indirect Field Costs$517.7M
Engineering, Construction Management, Home Office and Fee$517.7M
Contingency & Escalation$250.5M
Contingency$250.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.0M
Financing Cost$50.7M
Pre-production Cost$9.5M
Inventory Capital$10.8M
Total Capex$1.74B