Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Direct Field Costs$1.09B
Process Utilities$29.7M
Indirect Field Costs$337.8M
Report did not provide a further cost breakdown.
Contingency & Escalation$614.9M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.04B

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Purchased Equipment$113.9M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense$178.9M
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies$91.1M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs$27.6M
Total Capex$411.5M

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
Civil and Structural$157.7M
Piping and Ducting$219.2M
NGCC Base Modifications Equipment$23.0M
Exhaust Gas Recirculation System Equipment$60.4M
Gas Turbine Modifications Equipment$47.3M
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment$169.2M
CO2 Compression Equipment$60.9M
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment$27.2M
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCC$46.8M
Initial fill of CCS inventory (Solvent and Activated Carbon)'$29.9M
Labor$210.3M
Foundations$50.0M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency$192.4M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B