Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Fixed OpEx$60.7M
Report did not provide a further cost breakdown.
Variable OpEx$13.1M
Report did not provide a further cost breakdown.
Total Opex$73.7M

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Fixed OpEx$16.8M
Report did not provide a further cost breakdown.
Variable OpEx$43.9M
Report did not provide a further cost breakdown.
Total Opex$60.7M

Scottish Power / Longannet Power Station

Natural GasFEED· ScottishPower· 2011-04-01Project page ↗
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Fixed OpEx$28.1M
Maint. / property taxes / insurance$11.2M
Operating labor$5.1M
Admin & support labor$11.9M
Variable OpEx$10.3M
Consumables$9.7M
Waste disposal$0.6M
Total Opex$38.4M