Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Direct Field Costs$71.7M
Flue Gas Systems
Indirect Field Costs$6.7M
Engineering
Project Management
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$78.4M

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Modularization
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs
Total Capex$411.5M

Peterhead Power Station (Aberdeenshire)

Natural GasFEED· Shell· Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$331.4M
Solvent Pumping and Conditioning
Indirect Field Costs$89.7M
Indirect Field Costs
Engineering
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M