Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Devon Energy / Jackfish-1 Oil Sands
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
8.6%mol%
▸Direct Field Costs$71.7M
Module Shop Fabrication$16.3M
Site Installation$22.9M
Major Equipment$31.6M
▸Indirect Field Costs$6.7M
Engineering$2.2M
Project Management$4.4M
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$78.4M
Southern Company / Plant Barry
CO₂ captured
2,400,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
CO₂ concentration
99.0%vol%
▸Direct Field Costs$89.7M
CO2 Compression Equipment$27.5M
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies$59.8M
Dehydration$2.4M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$89.7M
Southern Company / Plant Barry
CO₂ captured
4,200,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
CO₂ concentration
99.0%vol%
▸Direct Field Costs$154.5M
CO2 Compression Equipment$48.1M
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies$102.0M
Dehydration$3.4M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$154.5M